Modular Pipe-Rack Structural Steel & Skid Fabrication QA/QC Supervision
CONSTRUCTION & INFRASTRUCTURE • COMPLIANCE & QA/QC SERVICES

Modular Pipe-Rack Structural Steel & Skid Fabrication QA/QC Supervision

Resident welding & NDT supervision, AWS D1.1 structural UT/MT weld checks, padeye examination, and shop protective coating inspection prior to site erection.

ASSET & CLIENT CONTEXT

Operational Context

Client Context
Industrial EPC Contractor (Anonymized)
Location
Ogun & Lagos Fabrication Yards
Asset Type
Heavy Structural Steel Pipe-Rack Modules & Lifting Padeyes

Inspection / Technical Challenge

Maintaining uniform weld quality, MTC traceability, and primer DFT compliance across multiple simultaneous structural bays prior to heavy road transport.

Scope & Execution Approach

Enforced strict ITP hold points from incoming steel heat-number verification through fit-up, preheat, shear-wave UT on full-penetration moment connections, MT on lifting padeyes, and SSPC-PA 2 DFT sign-off.

Site & Operational Constraints: High production throughput pressure and outdoor monsoon rain disruptions during shop primer touch-ups.

Documented Outcomes

  • Traceable heat-number, welder stamp, NDT, and coating records compiled into indexed module MRBs.
  • Lifting padeyes verified free of surface cracks prior to heavy rigging deployment.
  • Eliminated field fit-up and touch-up delays prior to site structural erection.
Engineering Takeaway

Mandatory fit-up and consumable-oven daily audits cut ultrasonic weld repair rates dramatically across heavy plate girders.

Field Photography

Modular Pipe-Rack Structural Steel & Skid Fabrication QA/QC Supervision field photograph 1
Modular Pipe-Rack Structural Steel & Skid Fabrication QA/QC Supervision field photograph 2
TECHNICAL & COMMERCIAL ENQUIRIES

Planning a Comparable Inspection or Coatings Project?

Share your asset details, applicable engineering codes, and target project window with our technical team to initiate a quotation review.